Community Information Meeting · What We Shared

Sioux County Data Center

We met Monday, August 10 at the courthouse in Orange City. Thank you for coming, for the questions, and for the pushback. This page is the short version of what we presented, and what happens next.

First meeting
Monday, August 10
Sioux County Courthouse · Orange City
Webinar
Monday, August 17
5:30–7:00 PM Central
Second meeting
Tuesday, August 25
American Reformed Church, 911 1st Street, Hull

What we're proposing

We build small. Think neighborhood hospital, not Mayo Clinic. We build in 10 MW blocks, and the project we're exploring here would be up to 25 MW, the same cap we've asked the County to write into its rules. The final size gets pinned in a county application, in public, where every number can be checked.

10 MW
The block we build in
Up to 25 MW
Project size: the cap we asked the County to adopt
40,000 sqft
Per 10 MW block, a movie theater's footprint
< 30 acres
Site size at full build
< 55 dBA
Noise at the property line
$100–375M
Investment, from one block to the full 25 MW build

Figures are the design estimates presented at the August 10 meeting.

Inside the building

Here’s what goes into a typical PathOne data center: how it’s cooled, how it’s powered, and how it’s protected and secured. Final design is set site by site.

Cooling

A right-sized, closed-loop system, designed for minimal water use. Temperature and humidity are monitored and managed around the clock.

Power

Two utility feeds into the site. The backup diesel generators are for emergencies only, never the main power source.

Fire protection

A pre-action, zoned dry-pipe sprinkler system, with early-warning smoke detection.

Security

Staffed daily and monitored 24/7, with cameras, controlled entry, and a team ready to respond right away.

The water picture

The water question is really a cooling question. We design for minimal water use, through closed-loop systems and a partner’s patented cooling technology.

The giant water numbers you may have read about come from evaporative-cooled hyperscale campuses, a different design at a different scale. That's not what we build, and we've asked the County to require low-water closed-loop cooling by rule.

Not all data centers are the same

"Data center" covers buildings that have almost nothing in common. The thousand-acre campuses and hundreds of megawatts that make national news are the hyperscale end of this table. We're the first row.

TypeLandPower
PathOneUnder 30 acres10 MW blocks, up to 25 MW
Small / EdgeUnder 25 acresUnder 25 MW
Regional25–100 acres25–100 MW
Hyperscale100–700 acres100–500 MW
Mega hyperscale700–1,000 acres500–1,500+ MW

Six protections we're asking the County to adopt

Rules come first. We presented six protections Monday night and asked the County to write them into its ordinance, so they bind us and anyone who comes after us. The Board holds the pen.

1 · Keep it controlled

Cap project size at 25 MW. Every project requires County approval. No exceptions.

2 · Protect neighbors

Strict noise limits at nearby farms and homes, quieter building design and sound barriers, downward-shielded lighting, and screened equipment.

3 · Protect water and farmland

Require low-water closed-loop cooling. Fix or pay for any damage to nearby wells. Favor industrial ground and lower-quality farmland over productive acres.

4 · Pay your own way

The developer pays for road damage and improvements, utility infrastructure, safety equipment and firefighter training, and independent studies and inspections.

5 · Benefit the community

Pay full property taxes. Take no local tax abatement. Make additional community investments, and publicly report water use and promised benefits.

6 · Stay accountable

Keep emergency and shutdown plans on file. Set money aside up front to remove the facility if it is ever abandoned. Violations can lead to fines or closure, with enforcement for the life of the facility, not just at approval.

Here is the one-page version. Print it, or keep it on your phone.

Taxes and jobs: the honest version

A facility this size pays full local property taxes, roughly 3.9% of building cost every year, and we've asked for no local tax abatement. On jobs: a 10 MW facility is not a jobs program, and we won't pretend otherwise. At full build it supports roughly 10–20 permanent full-time positions at strong wages, plus construction work while it's built.

What happens next

The big questions get answered here. We're collecting what came up at both meetings and what gets submitted through this page, and we'll publish written answers to the questions asked most.

The online webinar was held Monday, August 17, 5:30–7:00 PM (Central). Thanks to everyone who joined and asked questions live.

We held a second in-person meeting Tuesday, August 25 at American Reformed Church in Hull, the same format as our first meeting at the courthouse. Thanks to everyone who came out.

Nothing further is on the calendar right now. If we schedule another meeting, the date will be posted here. In the meantime, the form below is open and we read everything that comes through it.

Didn’t get to ask? Ask now.

Whether you were in the room Monday or couldn’t make it, send it in. We read everything, and the questions asked most get answered on this page.

Got it, thank you. We’ll answer you directly, and if it’s something others are wondering too, the answer goes up on this page.
Something went wrong sending that. Please try again in a minute.

Want a seat at the table?

We’re forming a Community Advisory Council: people who live and work in the community, hear project information first, ask the hard questions, and bring their neighbors’ concerns to the table. It’s open to supporters and skeptics alike.

Learn more and raise your hand →

Accessibility

If you need an accommodation to attend, send us a note through the form above and we’ll make it work.